We’re building a 39-kilometre water pipeline between Grantham and Peterborough.
It will eventually join up with the other planned pipelines to the north and south, forming the network that stretches from North Lincolnshire to Essex.
Update on works
Following our break over the winter months, due to ground conditions, we're back to pipelaying from Grantham to Peterborough. This will continue until mid-2027 and when complete, we’ll move into the reinstatement and commissioning phases of the project.
Supporting works
We are upgrading West Pinchbeck and Sutterton pumping stations.
Our impact
We continue to minimise our impact on communities and the environment, and work with local communities to deliver a legacy along the route.
If you would like to contact us about the Grantham to Peterborough section of the project, please email strategicpipelines@anglianwater.co.uk.
| What We're Doing | What It Means | When It's Happening |
|---|---|---|
Building completed |
This is where we’ll be laying down the pipe, building pumping stations and storage tanks and connecting everything together. |
Mid 2027 |
Restoring the land |
After building and testing the strategic pipe we’ll restore the land. |
Late 2027 |
Commissioning date |
We test water quality and pressure-test the pipeline with full quality assurance. Once complete, the pipeline is sampled and prepared for connection to the water network. |
Late 2027 |
Building completed
This is where we’ll be laying down the pipe, building pumping stations and storage tanks and connecting everything together.
Mid 2027
Restoring the land
After building and testing the strategic pipe we’ll restore the land.
Late 2027
Commissioning date
We test water quality and pressure-test the pipeline with full quality assurance. Once complete, the pipeline is sampled and prepared for connection to the water network.
Late 2027